Following the discovery of an issue on the Crinan Canal east of Bellanoch bridge, works will be taking place from Thursday 27th January 2022 until 25th March 2022.
The towpath between Dunardy Lock 13 and Bellanoch Bridge will be closed for the duration of the works.
This page will be updated as works progress.
Update 24th March 2022
Works are now complete between Lock 13 and Bellanoch bridge. The towpath is now open to public access.
Update 8th March 2022
The towpath east of Bellanoch bridge will now reopen on the 25th March 2022.
Update 18th February 2022
Due to a delay in works progress the towpath closure on the Crinan Canal, east of Bellanoch bridge will be extended until the 18th March 2022.
Scottish Canals apologise for any inconvenience caused.