The Claypits Local Nature Reserve – latest updates

Update 21 January 2021

Following the Christmas shut-down period and in line with Scottish Government guidance, construction works recommenced on the Claypits project in North Glasgow on 11th January. Scottish Canals continues to closely monitor the restrictions and all works will continue to reflect the current Covid-19 guidance.

Our contractors are currently on site and are working hard to finish the path works and SUDS infrastructure within the Claypits Nature Reserve in time for the spring/summer season. Work will also begin on the Garscube Link paths between Garscube Bridge and Garscube Roadd opposite Woodside Health Centre during this period.

While the second phase of works is underway, access for towpath users will still be available between Panmure Gate (the yellow brick road) and Garscube Bridge. Please take care as surfaces may be slippery due to the winter weather.

Update 8th December 2020

Since opening Garscube Bridge and Panmure Gate Link in early October there has been additional works carried out in preparation for the site opening of the remainder of the Claypits Nature Reserve in early Spring 2021.

The space around the new pond is having the surface of a necessary access area being overlaid with soiling and seeding to integrate it into the overall landscape, and the pond itself has been planted with reeds in anticipation of the return of wildlife to the new wetland area. Work across the site has inevitably resulted in some remedial works being required.   The current temporary protection is being removed from the spine path at Panmure Gate Link (the yellow brick road) and further assessments of the pathway will be carried out through December, and work carried out on it prior to the site reopening.

On the upper pathways, There is ongoing construction along the primary path at the glade area where we have placed a featured marker stone, highlighting a view point to the west. This path will connect back to Ellesmere Street entranceway, construction of which is also ongoing. The planting schedule for the overall site has commenced but was unfortunately affected by the COVID restrictions and hence delayed. As a result, areas of the site will continue to need vegetation regrowth even at the time of the site reopening in spring. As part of the planting plan, we are currently working on substantial seeding and planting, including planning for 700 young trees and shrubs to be planted by members of the community

In early December, Scottish Canals in partnership with ASA recruitment advertised a Community Development Manager role. This role will fill a vacancy that has existed over the summer, and the successful candidate will work alongside the local nature reserve management group (LNRMG) ahead of the main site opening.

Update 12th October 2020

Today, Scottish Canals has officially opened Garscube Bridge and Panmure Gate Link in the North of Glasgow, connecting communities at either side of the historic Forth & Clyde Canal.

The completion of works on the new bridge and link carried out by McKenzie Construction marks an important milestone in the delivery of the Claypits project. Today’s opening will connect the communities of Panmure Gate and Woodside, giving residents direct access to Scotland’s sustainable transport network along the Forth & Clyde Canal.

The remainder of the path network on the Claypits Local Nature Reserve will remain closed until Spring 2021 as works progress in this section of the project.

Update 19th August 2020

Since the lifting of Scottish Government Covid-19 restrictions, our team and contractors have been back on site to complete of works at Claypits which will reopen The Forth & Clyde Canal in North Glasgow and it’s surrounding areas to walkers, runners and boaters.

Following the closure of the waterway earlier in the year, we are pleased to announce that waterway navigation, access to the Garscube pedestrian bridge, sections of the Claypits Nature Reserve and Panmure Gate and pontoons will be accessible towards the end of September once the works in these areas are completed. In particular, the completion of Garscube Bridge which will reopen The Forth & Clyde Canal in North Glasgow to boaters, while walkers, runners and cyclists continue to be able to use the towpath at Garscube, and will soon be able to use the bridge and Panmure Link too.

Recent works include piling to accommodate pontoons, footpath maintenance, and the lift in of the Garscube pedestrian bridge and can be seen below.

Scottish Canals continues to work with partners and surrounding community groups in organising the opening of the Garscube Bridge and celebrating the vital link to nature it will provide for the surrounding area. We ask that members of the public continue to follow signage on site as we work to reopen the larger area in early 2021.

Upcoming works yet to be completed include additional footpaths and landscaping in the Claypits, Garscube Link which will connect the towpath to Garscube Road and the new health centre, and ongoing work to the Sustainable Urban Drainage Systems (SUDS) which supports the development of new homes in adjoining areas. Updates will be posted on our website and on our social channels.

 

Update 8th July 2020

Our teams are currently working on site at the Claypits site and Garscube Bridge, and expect that works will be completed to allow boat navigation in this area by the end of September.

We apologise for any inconvenience caused for both boaters and towpath users during the delay caused by these works. Following the three month delay caused by Covid-19 at the end of March, we appreciate your patience and understanding as our teams and third party construction partners work to find new ways of working safely.

 

Update 12th June 2020

Following Scottish Government phasing of lockdown easing, we are pleased to be able to restart works on the Claypits site and Garscube Bridge this month. The site will reopen on Thursday 18th June, with works commencing on Panmure Gate pontoon and path structure, as well as Garscube Bridge foundation works.

As part of the works, we will be required to once again close the towpath between Applecross Street and Firhill to allow for the construction and installation of Garscube Bridge. The closure will last approximately four weeks, with a diversion in place – we will share exact closure dates once confirmed.

Update 10th March 2020

Shortly our teams and constructors will be undertaking the felling of a tree which is within the canal infrastructure itself to ensure no damage is done to the waterway. These works will be supplemented by a programme of tree planting between Panmure Gate and Ellesmere spur which will see approximately 70 new trees planted.

Update 6th March 2020

Please note that the towpath between Applecross Street and Firhill will be closed from the 16th of March for approximately three weeks to accommodate works on the Garscube pedestrian bridge. A diversion will be in place for pedestrians and cyclist use as seen below.

Update 26th February 2020

Please note that the canal will remain closed to transits until the end of April 2020 due to ongoing works on the Garscube pedestrian bridge. While we have taken every effort to complete the project during the off-season, a delay has occurred due to poor weather conditions and engineering challenges related to the technical nature of the build.  Our contractors are working 7 days a week offsite to create the necessary components for installation

Towpath closures are also expected during this period, information about dates and diversions will be shared in due course.

Update 21st January 2020

Works have started on the concrete foundations to support the Garscube Bridge structure. There will be approximately 115m3 of concrete poured to form the 600mm thick continuous slab and it will be completed by close of play Tuesday 21st January 2020.

Update 15th January 2020

As part of the ongoing nature reserve improvement works Scottish Canals will be mobilising plant and machinery to operate in the canal around the Firhill Basin. Works are due to commence on Monday 3rd of February for 3-4 weeks and will be managed adjacent to the Firhill Road bridge. Some users of the tow path may experience some disruption during the works, however the towpath will remain open.

The current canal closure will also include the stretch up to and including the Firhill basin area during this time.

Update 20th November 2019

The towpath from Firhill to Applecross is now open, and the works on the Garscube pedestrian bridge are well underway. Take a look at the progress so far below.

 

 

Update 4th November 2019

As works on the Garscube Bridge progress, we will be closing the towpath from Firhill to Applecross from Monday 25th November to Sunday 15th December. This will allow works to be undertaken on the bridge foundations. Dates are subject to change; please keep up-to-date by bookmarking this page or visiting @scottishcanals on Twitter.

The below map shows the diversion route in place throughout the towpath closure period

Update 18th October 2019

As part of the ongoing works at Garscube Bridge, Panmure Gate and Firhill, we will be required to close the towpath for a period throughout the works, beginning in November 2019.

We will share exact dates of closure once these are known.

Download the latest plan for The Claypits

Update 10th October 2019

Due to ongoing works at Applecross Street, the car parking spaces directly adjacent to the stores building will be closed from Monday the 14th of October for approximately one week.

Update 24th September 2019

The piling rig for the  pontoons at Panmure Moorings will be mobilising 1st October, and similarly at Panmure Gate pathway on the 8th October. This work will affect both canal traffic and towpath access due to plant access requirements at Firhill. The ongoing piling will take place throughout October.

Update 22nd August 2019

Works on the new Garscube Bridge will begin on Monday 26th August. These works will impact both navigation on the canal and on the towpath during the following key dates:

  • Monday 26th August 2019 – duration of roughly two weeks – Channel realignment and silt removal at Firhill may produce materials and debris in the water which will be managed by Mackenzie Construction.
  • Thursday 29th August to 4th October 2019 –Disruption at Canal House, Applecross Street.  The ongoing drainage works will involve closing the east section of the Applecross car park on Thursday the 12th of August for two days. There will also be no access to the car park over the weekend of the 21st and 22nd September. Similarly, the north west parking bays will not be available from the 23rd of September to the 4th of October. Please note that due to clashes with other works in the area, the works surrounding Canal House, Applecross have changed. These dates have been updated to reflect the current timescales.  
  • Monday 9th September until Sunday 15th September 2019 – Works start on the Garscube Bridge which will reduce the number of boats able to pass through this section of the canal. Please call the Boat Movements Line on 07810 794467 if you are planning to travel through this area during these dates.
  • Monday 16th September 2019 until March 2020 – Channel closure will disrupt navigation along the Forth & Clyde Canal between Firhill Basin and Applecross. Sea-to-sea navigation along the Lowlands will remain unaffected by this closure.

 

Main paths closure, 4th February 2019 – spring 2020

The main path in The Claypits (known as ‘The Yellow Brick Road’) will be closed from 4th February until spring 2020.

This closure is to allow a wide range of improvements to the area including: the construction of a new foot and cycle bridge over the Forth & Clyde Canal; new and improved pathways; new wildlife habitats; the creation of viewpoints; the installation of fishing pegs; improved drainage in the surrounding area; and new gateways at Panmure Street, Garscube Road, and Ellesmere Street.

An alternative route is available via the Applecross Street and Ellesmere Street footpaths during the construction works.

We appreciate everyone’s patience during the works and look forward to welcoming you to explore The Claypits.

This page will be updated with further information as it becomes available. You can also follow us on Twitter @ScottishCanals for updates.

Share this Story