Our scheduled winter works programme for 2019-20 is outlined below. This planned investment in our canals is essential to safeguard them for future generations.

Canal and towpath disruptions will only happen on specific dates/times within the overall project; we will insert specific dates in place of ticks when they are known.  Further information on each project will be available by clicking the project name or via the what we are doing  page.
Dates are subject to change. Further dates will be added once confirmed. The works schedule will be updated on a monthly basis.
Location 3rd Party Works Towpath Disruption Canal Disruption Dates
Caledonian Canal
28/10/19 – 27/03/20
Laggan Bridge ✔️
Banavie Bridge ✔️
Banavie Rail Swing Bridge ✔️
Corpach Jetty ✔️
Corpach Marina ✔️
Fort Augustus phase 2 ✔️ ✔️
Kytra Embankment 04/11/19-27/03/20 ✔️
Fort Augustus Bridge ✔️
Aberchalder Bridge ✔️
Corpach Rail Swing Bridge ✔️
Inverness West Link ✔️
Muirtown Embankment ✔️
Crinan Canal
26/10/19 – 27/03/20
Bellanoch Bridge Mooring ✔️
Ardrishaig Holding Pontoon
Lock Gate Surveys ✔️
Crinan Manual Bridges
Forth & Clyde Canal
01/07/19 – 05/11/21
Stockingfield Bridge ✔️ ✔️
Camelon Embankment
Rowantree Bonnybridge Embankment
Bishopbriggs Culvert
Brightons Burn Aqueduct
Garscube Bridge 25/11/19-15/12/19 ✔️
Firhill Pontoons ✔️
NGIWMS Commissioning
Union Canal
04/11/19 – 19/06/20
Glen High Bridge ✔️
Wilcoxholme Embankment ✔️ ✔️
A720 Aqueduct test ✔️ ✔️ ✔️  09/11/19-10/11/19
A720 Aqueduct Closure ✔️ ✔️ ✔️  09/11/19-10/11/19
Winchburgh Marina & Footbridge ✔️ ✔️
The Falkirk Wheel
04/11/19 – 13/12/19
Winter Works ✔️

*Dates are subject to change. Further dates will be added once confirmed.