Main

Information for boaters

Please note that navigation between locks 3 (Grangemouth) and 16 (Camelon) is now suspended until 23rd April 2027. If you have any questions about the upcoming works programme and impacts upon moorings, please contact our Moorings Team direct at moorings@scottishcanals.co.uk. For questions about impacts on navigation, please contact Enquiries@scottishcanals.co.uk

Overview 

Twenty-five years ago, a momentous civil engineering project rescued Scotland’s Lowland canals from dereliction. Using an investment from the National Lottery, the Millennium Link project refitted the Forth & Clyde Canal and restored the historic link to the Union Canal.  

Since then, the canal network has brought in billions of pounds in investment, enabling the development of major attractions: The Falkirk Wheel, Stockingfield Bridge and the Kelpies. They are playing new roles in our society too through initiatives like the Glasgow Smart Canal which provides additional drainage solutions for brownfield sites, freeing up space for 3,500 new homes in the affordable and mid-range category in the north of the city. 

While the Forth & Clyde Canal is now a thriving space, by the start of 2024, our inspections revealed that the infrastructure along the Falkirk Flight required extensive upgrades, repairs and gate replacements. The old oak lock gates installed on the Falkirk Flight during the Millennium Link project were deteriorating badly: the downstream gates needed replacement, and the upstream gates needed repair. Upgrades were needed along the length to improve water controls, repair crumbling masonry, and carry out repairs within the canal bed. 

The current engineering programme is the biggest on our network in 25 years, representing a major investment in the future of our Lowland canals. 

First phases of the programme – 2025/2026

Extension of the project to April 2027

When we designed the programme for 2025/2026, we had a limited view of the canal. With the canal dewatered, we have also had the opportunity to conduct detailed inspections of assets normally submerged under water. This has revealed more work to do, including further gate replacements and repairs, and a series of other works along this stretch of canal. 

With the end of the project set for August 2026 and a growing list of gates and repairs needed along the canal, we had a decision to make. We could re-water the canal only to return within a year or two and dewater once again to conduct the additional repairs and gate replacement. This would be a costly choice that would bring disruption to the community and boaters for longer. The alternative was to keep the canal dewatered until 23rd April and capture all the additional and urgent gate replacements and repairs into this one period. 

The extended scope includes: 

  • Replacement of downstream gates at Lock 4 (Abbots Road). With a 26 week lead time for gate manufacture, new lock gates are scheduled to arrive in February 2027. Lock 4 top lock gates will old life expired planking removed and re-planked.
  • Replacement of the upstream gates at Lock 13. The gates are significantly decayed and would be at risk of failure in the near future without replacement now. We will use a more robust hardwood timber than the traditional oak this time around. 
  • Repairs to the historic masonry quoins (the curved recesses where the gate mechanisms operate), replacement of mechanisms, re-planking of upstream lock gates, and repairs to masonry and embankments along the length of the canal. 
  • Clean-up and rewatering of the canal, a process that takes many weeks and involves continuous monitoring and adjustment of water controls along the canal. Our Operations Team will also need to conduct dredging and sediment removal at the two sea locks.  
https://d1hxd0sho1wxko.cloudfront.net/production/imager-transforms-cache/general/456494/east-reach-map-locks_2a8e16ff560affca9cefb10160848c00.jpg

Latest Updates

Friday 16th October 

With much of the programme now delivered on the Camelon section of the canal, the focus of the project has now shifted to Lock 4 (Abbots Road) and the Grangemouth end of the canal. Our contractor's site compound is now located at Lock 4, and their current activities are:

  • Preparing Lock 4 and Lock 13 for the replacement gate installation
  • Installing stop plank grooves at Lock 4 preparatory to rewatering the canal up to this point (see the below images)
  • Repairing the embankment near to Lock 5 and installing leakage protection
  • Encapsulating the historic timber floors at Lock 4 in membranes and laying a new concrete floor

With the installation of stop plank grooves, which allow us to dam individual lock chambers, we will be able to conduct upcoming repairs without the need to have the entire Falkirk Flight dewatered.

Saturday 15th August

Thank you to everyone who attended our Community Pop-In Day at Camelon Community Centre! We had a good attendance from members of the community with plenty of questions about the project and the next steps. If you were not able to attend on the day, you can find our contact details and answers to some frequently asked questions below. 

https://d1hxd0sho1wxko.cloudfront.net/production/imager-transforms-cache/general/509338/camelon-community_2a8e16ff560affca9cefb10160848c00.jpg

FAQs

Towpath Diversion Maps

Enquiries

If you have any questions or concerns, please contact us at enquiries@scottishcanals.co.uk or on 0141 332 6936  (Monday to Thursday 8.30am-5pm, Friday 8.30am - 4.30pm). 

half-circleicon-accessibleicon-adult-onlyicon-arrow-45icon-arrow-whiteicon-arrowicon-articon-boatingicon-campingicon-chandleryicon-charge-pointicon-checkmark-tickicon-chevron-thinicon-chevronicon-closedicon-closureicon-community-consultationicon-crossicon-cyclingicon-de-masting-craneicon-dog-friendlyicon-dog-walkingicon-downloadsicon-educationalicon-elsanicon-engineering-marvelicon-environmentalicon-eventsicon-facebookicon-family-friendly-pathicon-family-friendlyicon-fishingicon-food-drinkicon-fuelicon-grid-viewicon-hamburgericon-health-wellbeingicon-heritageicon-instagramicon-land-activitiesicon-landscaped-areaicon-laundryicon-linkedinicon-living-on-watericon-location-pinkicon-locationicon-menu-crossicon-navigation-affectedicon-nessieicon-newsicon-no-campingicon-no-swimmingicon-overnight-staysicon-paddlingicon-parkingicon-photo-pointicon-placemakingicon-playicon-plusicon-point-of-interesticon-pump-outicon-quotesicon-refuse-disposalicon-runningicon-safetyicon-searchicon-shoppingicon-showers-toiletsicon-storage-shedsicon-sustainabilityicon-swimmingicon-tickicon-ticketicon-toilets-neutralicon-toiletsicon-twittericon-volunteeringicon-walkingicon-warningicon-waste-oil-disposalicon-water-activitiesicon-water-supplyicon-wildlife-watchingicon-youtubelogo-bluelogo-white